  • Description: The scope of this work is to move the Joel D. Valdez Main Library from its current location at 101 N. Stone across the street to the former Wells Fargo Bank building at 150 N. Stone Ave. The Downtown Library will receive a major renovation to optimize its space for patrons and the administrative staff. The library acquired the 50,000-square-foot Wells Fargo Building, and the two ancillary buildings and an adjacent parking garage. A more detailed timeline for the project is coming soon.
  • Design Firm: Line and Space
  • Contractor: Sundt
  • Project Schedule: Estimated to complete and open to the public in 2029
  • Project Budget: $26 million

Milestones/Phases

Design Phase

Carosel showing public surveys being collected and an open house event

Item 1 of 2

Public Outreach/Programming

 

Construction Phase

Prepare for Opening

Open to the Public

Blogs about the Future Downtown Library Branch

Pima County purchases the Wells Fargo Building

County Board of Supervisors approved the purchase of the former Wells Fargo building for future replacement for Joel D. Valdez Main Library